patching...
Breaking: Man, 37, Injured In Truck Crash In Wall »
Welcome back, Patch Blogger!

Ocean Avenue

Friday, May 17, 2013

Countdown to Memorial Day

Countdown to Memorial Day As Belmar Installs Boardwalk Railings, Bathrooms

Photo gallery of construction leading up to grand reopening

The signs along the Belmar beach and boardwalk still say "Closed," but not for much longer. Less than a week remains until the ribbon-cutting on the Belmar beach and boardwalk. This week, the beachfront bustled with final touches on the four beach playgrounds, striping along Ocean Avenue and installation of boardwalk railings.  Temporary trailers will be in place for concessions, and bathrooms. Though a lighting design is approved, if the project is not complete the use of alternative, temporary spotlights will be in place to light up the boardwalk, officials said. Here is a gallery of all the recent activity along the beachfront.

paul

10:49 am on Friday, May 17, 2013

Are there any plans to open Ocean avenue between Belmar and Spring Lake   more ›

Thursday, May 9, 2013

Traffic on the Shore

Traffic: Oceanfront Closed in Lake Como, Manasquan Striping Parking Lots

Projects throughout the area

A round-up of traffic projects in the area: Manasquan: The beachfront of Ocean Avenue east of First Avenue is closed for the beach headquarters reconstruction. The borough will also stripe the parking spaces for the First, Second and Third Avenue parking lots. The lots will be off-limits during painting hours. Ocean Avenue: The southernmost blocks of Ocean Avenue will be the last to reopen in Belmar, but portions of Lake Como are closed for pipe construction there. In Belmar, Ocean Avenue is open from Avon through 17th Avenue. The boardwalk is closed until railings are installed. In Avon, the eastern sidewalk is closed for boardwalk reconstruction along Ocean Avenue. Parkway work continues: The Wall rest stop's fuel station remains closed …

Comment_arrow

Beryl Cusic

9:09 pm on Thursday, May 9, 2013

I was just gonna say the same thing.   more ›

Wednesday, May 8, 2013

Lake Como Pumping Station Work Continues

Ocean Avenue closed for construction

Ocean Avenue in Lake Como remains closed as crews work on the oceanfront pumping station. Work continued this week to build the facility between Belmar and Spring Lake.  (Photos by Paul Spennrath)

Comment_arrow

Dame Bridgid

4:17 pm on Wednesday, May 8, 2013

Correct. A fail safe for the pump losing power should follow the K I S S rule.   more ›

Wednesday, April 24, 2013

Spring And Reopened Streets Brings Activity to Belmar Oceanfront

Photo gallery of activity and opened Ocean Avenue

Though several blocks are still closed, a large portion of Ocean Avenue in Belmar is open and bicyclists and pedestrians are taking to the oceanfront. For most of the winter, Ocean Avenue was closed due to Hurricane Sandy reconstruction of the boardwalk. But now that boards are lain for much of the project, many blocks were reopened and it's the southernmost portions of the roadway that remain closed in Belmar. Here's a gallery from local photographer Paul Spennrath of some of the activity.

Dame Bridgid

9:32 am on Thursday, April 25, 2013

I am walking 24 minutes in rehab now. I am tired of looking at walls. Time to lace up my sneakers & start alternating walking & running where I can hear the seabirds cry. Back to the beach!   more ›

Thursday, April 18, 2013

Belmar To Open Ocean Ave. Through 17th Ave. on Friday

More blocks opening now that boardwalk work progressing

Belmar plans to open Ocean Avenue up to 17th Avenue, on Friday, removing barriers from another portion of the oceanfront road packed with construction since Hurricane Sandy. But now that construction has progressed south of 17th Avenue, vehicular access will be restored to the road, Mayor Matt Doherty said. Now, vehicles can drive up to 10th Avenue before facing a detour. Another 7 blocks are expected to open Friday. Boardwalk construction crews' lumber and equipment closed Ocean Avenue much of this year, as the borough worked to rebuild the boardwalk destroyed by Hurricane Sandy. But the boardwalk north of 10th is now all lain, and the road and some parking was opened up as work was complete.

Dame Bridgid

8:03 pm on Friday, April 19, 2013

I saw the heavy construction equipment they had on Ocean. Mixing it with other vehicle traffic would not have been wise, charlie. Watch some of the time elapse construction work & see what I mean. You seem fixated on wanting a beach with no boardwalk... Like that Sierra Club dork who forced the town to use less ecologically sound materials, or face a court case from their deep pockets parent …   more ›

Wednesday, April 10, 2013

Hurricane Sandy

More Blocks Now Open For Traffic On Ocean Avenue in Belmar

First through 10th now open after Hurricane Sandy boardwalk construction is complete

Concrete barriers and detour signs are becoming fewer in Belmar. More of Ocean Avenue is now open: you can now drive 1st through 10th avenues. The additional blocks of the roadway opened Tuesday. Mayor Matt Doherty said last week that Ocean Avenue access was planned, to open five more blocks to traffic in about seven days. For several weeks, vehicles have been able to drive from 1st to 5th, but then faced a detour as the beachfront road was closed south of 5th due to the ongoing construction. Now, drivers can travel as far south as 5th before meeting a new detour west. Ocean Avenue was closed since an October evacuation, then through much of March for construction along the Hurricane Sandy ravaged beachfront. Construction crews began …

Monday, April 8, 2013

Hurricane Sandy

More Boards in Belmar; More Construction on Avon Boardwalk

Photo gallery of construction

The oceanfront of both Belmar and Avon are full of ongoing construction, with Belmar laying more boards for its boardwalk and Avon adding pilings to its boardwalk reconstruction. Check out this gallery of photos from April 2-7 from resident Paul Spennrath to see more of the construction unfold.

Dame Bridgid

7:08 am on Monday, April 8, 2013

Belmar was very wise to get a head start on the construction. After the boardwalk is finished there will be enough time to clean up & do plantings. That will allow Belmar to present a much better appearance to guests who come to enjoy the Summer here. With all the important visitors & publicity Belmar is expecting this year, that will possibly mean more work will be available for area residents …   more ›

Thursday, April 4, 2013

Hurricane Sandy

More of Belmar's Ocean Ave. Should Reopen in Seven Days, Mayor Says

Road opened through 5th avenue currently, but much remains closed

More access to Ocean Avenue in Belmar could be coming as early as next week. Officials at the local and county level are working to reopen another five blocks of the oceanfront road, Mayor Matt Doherty told Patch last night. Late in March, barriers were removed from Ocean Avenue at 1st through 5th Avenues allowing pedestrian and vehicular access. Some parking was restored though much of the spaces are not open. Doherty said officials are working to open the road through 10th Avenue in seven days. The roadway was originally closed after Hurricane Sandy for safety reasons as debris and damage littered the area. It remained closed as construction crews entered the area to remove debris, sift sand and rebuild the boardwalk. Doherty said …

Dame Bridgid

11:50 pm on Sunday, April 7, 2013

Had Ocean Avenue been open to traffic, there would have been gawkers in vehicles slowing the work crews. Didn't you watch the video of just how rapidly the pylons were being driven in...One every 5 minutes! Now imagine how much 18 wheel truck traffic was needed just to supply pylons that quickly. Mixing spectator vehicles with those & other heavy construction equipment like sand sifters would …   more ›

Thursday, March 28, 2013

Hurricane Sandy

PHOTOS: Avon Beachfront Progresses With Boardwalk Pilings

South side has new pilings

Just before the newly opened Ocean Avenue bridge, construction on Avon's boardwalk is progressing behind high chain-link fence. New pilings are in place there, but the chipped cement blocks of the wall adjacent to the sidewalk, and older, damaged pilings are the signs that mark further construction left on the Avon beachfront. Here are some photos from this week on Ocean Avenue in Avon.

Jared Winterton

5:55 pm on Tuesday, April 30, 2013

It'll be beautiful when the boardwalk is finally completed. I'm looking to put a chain link fence up in my home. Does anybody have any experience with chain link fence builders in Vancouver? I'd rather by from someone recommended then some stranger. Thanks.   more ›

Monday, March 4, 2013

Hurricane Sandy

Onlookers Visit Belmar's Oceanfront For One Day of Access

Ocean Avenue will be closed daily through construction

The ocean came over the boardwalk, took its boards inland during the surge, smashing homes and businesses with debris, sand and feet of water. The clean-up and rebuilding of Belmar's beachfront continues months after Hurricane Sandy devastated much of its property, and since the storm Ocean Avenue has remained closed. But that changed Sunday, when local officials decided to open up the north-south corridor to vehicle and pedestrian traffic to help mitigate the expected crowds for the day's St. Patrick's Day Parade. In one day, the beachfront saw onlookers snapping pictures and climbing the unfinished boardwalk. Come sunset, crews began restoring cement barricades and chain link fences to again prevent access. Now, Monday, construction …

Got a Hot Tip?

Patch Picks